Tuesday, November 17, 2009

METHOD STATEMENT FOR BORED PILING

GENERAL

The method statement for bored piling below describes the whole construction procedures including material and equipment required for the construction of bored cast-in-situ piles

Detail of the procedures contained herein maybe reviewed periodically and modified based on actual requirement

The piles to be constructed will be of a nominal specified diameter, bored through overlying soils to found in the bedrock strata or remain in the soil to act as shaft friction and end bearing piles. The piles are designed by the Engineer to resist axial compressive loads.

BORED PILES CONSTRUCTION

The pile boring operations shall be performed using the suitable rotary drill rigs depends on the diameter, depth, soil condition and construction method.

If necessary, the bore-holes shall be stabilized with a temporary casing in the upper layer (depends on soil and site condition) .The length of the casing will be determined from the actual soil condition encountered on site. Bentonite shall be used for unstable subsoil condition and for piles equal and more than 1800mm diameter.

SETTING OUT

The location of permanent bored piles shall be set out and pegged by the subcontractor’s surveyor based on approved setting out drawings from consultant and control points at site. The surveying details of each location to be recorded incorporating reduced level and coordinates.

Each individually surveyed pile position shall be protected from disturbance prior to commencement of boring works.

Two reference points to be installed equidistant at not less than 2.0m from the pile centre location. A pilot hole of about 3-6metre deep shall be drilled at the pile location. The eccentricity and alignment of the pilot hole is then checked.

DRILLING

Prior to commencing any operations, the client representative will be required to verify all associated technical information such as presence of services, pile coordinates, platform and cut-off levels, validity of drawings etc.

Then, if necessary, after accurately setting out of the pile location by a land surveyor, a temporary casing will be set in position with length of casing to be determined from ground condition. The vertical accuracy of the casing will be checked during the installation process using 2 numbers of plumb bob.

Excavation of the soil inside the casing/bored holes will be carried out using the rotary kelly bar and the auger or bucket method.

The drilling process will be continued to the designed founding depth or to the commencement of rock head level by using augers and drilling buckets.

Pile lengths shall be as per the current construction drawings or as otherwise instructed by the client/Engineer.

At the point of encountering the rock (as define in the contract specification) head level, for examples, where the soil drilling tools are unable to penetrate the strata any further, boring shall cease in order that the client’s representative may verify the occurrence and confirm the rock socketing criteria.

For drilling through rock, rock drilling tools shall be applied. This shall include rock auger, core barrels, (round shank, roller bit) cross cutters and where necessary, chisels.

The final toe level of the pile shall be verified by the client’s representative. A detailed record of all encountered ground conditions together with the associated times and type of equipment and materials used will be recorded in the ‘Pile Bore Log’.

Upon reaching the final depth, loose and re-moulded material and debris will be removed using ‘cleaning bucket’. The cleaning bucket is a specially design flat bottom bucket which will pick up all the loose material at the bottom of the hole. The based of the hole shall be checked by the measuring the depth of the base.

BENTONITE

The bentonite is delivered to site in 50kg per bags, which are stored under cover. The bentonite is mixed by high turbulence mixers and the slurry is stored in a pool. The size of the pool shall have a storage capacity of about 400 cu.m.

A laboratory is provided on site for regular testing of the slurry. The minimum frequency of testing and the acceptable range of physical characteristics of the bentonite slurry are given in Appendix 1. Laboratory reports are kept during the construction period.

Apparatus available in the site laboratory includes the following:

1 mud balance (density test)

1 marsh cone ( viscosity test)

1 sand screen set ( sand content test)

Paper for measuring Ph

Contaminated bentonite slurry will be discarded by mixing with the earth and transport to dumping area.

Bentonite will be used as a drilling fluid to stabilize the bored hole. During the boring process, the bentonite slurry is kept as high as possible within the casing and well above the existing ground water

Upon completion of boring, the bottom of the bored hole is thoroughly cleaned with the cleaning bucket prior to recycling of the bentonite. A submersible turbine pump attached to the tremie pipe is lowered to the bottom of the bored hole. The bentonite, loaded with soil particles in suspension, is drawn off from the bottom of the bored hole and recycled through a Caviem or equivalent recycling unit. The process is continued until the bentonite arriving from the base of bored hole had been flush out.

INSTALLATION OF STEEL CAGE

The reinforcement cage will be fabricated in lay-down sections. The length, type and size of the steel cage will be according to contract drawings and specifications.

The cages will be provided with stiffening rings and others accessories to enable handling, lifting and installation without permanent deformations.

Cages will be installed into the bored hole using a service crane of the required lifting capacity

Concrete spacers wired to the cage shall provide lateral support and ensure adequate concrete cover. Spacers shall be placed at 3 equal levels of each 12m cage with 3 nos at each level. If the diameter of bored pile more than 2000mm the spacers shall be placed more than 3 nos to be advised by consultant representative.

CONCRETING

All pile shall then be concreted by using the ‘tremie’ method.

Concrete of higher slump (=175mm+25mm) shall be used for ‘tremie’ method. The self-compacting mixed concrete will be discharged through a tremie pipe, which is lowered centrally to the bottom of the bored hole prior to filling it with concrete. Concrete level of the borehole was recorded after each concrete truck discharged and graph will be plotting against theoretical.

One length shall be continuously embedded in the concrete during this process to ensure that the discharge of concrete is below the level of the impurities, which might be present in the top part of the rising head of concrete.

All testing and sampling of the concrete shall be carried out as instructed by the Engineer or Engineer’s representative. A complete record of all cubes taken shall be maintained in a proper form and slump test results shall be recorded on the ‘Delivery Order’ and the ‘Pile Bore Log’. All compressive concrete tests will be carried out at the supplier’s laboratory and independent lab. The client will be notified of the dates of the test by regular issuance in order the tests maybe witnessed.

For a continuous assurance of concrete quality and integrity, concrete will be poured to minimum 0.6m above the theoretical cut-off level.

All completed piles shall be temporarily barricaded and to be backfilled to ground level with a suitable material the next day.

SPOIL REMOVAL

Spoil from piles will be cleared from the boring locations by means of an excavator as boring proceeds.

Depending on the volume of spoil excavated, it will be removed to stockpile area or spoil pit, for drying before loading and removed off-site.

12 comments:

Anonymous said...

I am very happy to read your article, it would be my reference to improve our work.

Thank you.
http://www.arsitek-banten.com/

aK said...

Dear syima, your article very much helpful. Im using it as reference in writing my internship report. TQVM

Unknown said...

this was exactly what i needed.

Thank you very much.

Unknown said...

very good and clear

Yam Basnet said...

Which international stander followed for CIP BORED PILES work

Yam Basnet said...

Which international stander followed for CIP BORED PILES work

Unknown said...

thankyou for this. very important

DEETECH said...

thanks sir
u r doing such a great job
keep it up

SCREW PILING SYDNEY said...

This placed up might be very beneficial for us. due to the reality we have got a number of tips and suggestions from this placed up. thanks for this superb post proportion.
When Only the Best screw will do. When and where to save on piling costs with screw piles.
We provide services of Besment waterproofing, concrete repair, footings, subsidence, basement underpin articles, basement walls, retaining walls, shoring, spray concrete, underpinning, grout injection, house underpinning(sydney), underpinning services, foundation repairs, basement garages, house restumping and ventilation sub-floor.
micro piers

Just Do It said...

May I know how do you do with the temporary casing ? Remove and recycle ?

Unknown said...

excellent guide for construction ,thx

Unknown said...

THANK YOU :)

Post a Comment